DSSSB - 29 August 2019 (Shift-2)
Non Nursing Subjects
Hard

A can do a work in 24 days and B can do the work in 32 days. If they work together for 8 days, what fraction of work is left?

Appeared in: DSSSB - 29 August 2019 (Shift-2)

Explanation

  • The core concept is to calculate work rate as the reciprocal of time (e.g., A's rate is 1/24 of the work per day).
  • When working together, their individual rates are added. The combined rate is 1/24 + 1/32 = 7/96 of the work per day.
  • The amount of work completed in 8 days is the combined rate multiplied by the time: (7/96) * 8 = 7/12.
  • The question asks for the work left, which is the total work (1) minus the work done: 1 - 7/12 = 5/12.

Why Other Options Were Wrong

  • Option A: This fraction (1/3 or 4/12) is an incorrect calculation and does not correspond to either the work done or the work left.
  • Option B: This is the fraction of the work that was completed by A and B in 8 days, not the fraction of work that is left.
  • Option D: This fraction (1/2 or 6/12) is an incorrect calculation. It is close to the correct answer of 5/12 but is not precise.

Related Visual

Visual explanation — Related Visual
Clinical Relevance
  • Nursing practice connection: This is primarily an exam-oriented knowledge point with limited direct bedside application, so retain Work and Time problems involving combined work and remaining work as background academic context rather than a clinical decision trigger.
  • This question tests foundational mathematical skills (fractions, rates) which are essential for various calculations in nursing, such as medication dosage, IV drip rates, and interpreting patient data charts.
  • Accuracy in fraction calculation is a critical patient safety skill to prevent medication errors.
  • What if? If they worked for 12 days instead of 8, the work done would be (7/96) * 12 = 7/8. The work left would then be 1 - 7/8 = 1/8.
How to Approach the Question
  • First, identify the time each person takes to complete the work individually (A = 24 days, B = 32 days).
  • Calculate the rate of work for each person. The rate is the reciprocal of the time taken (Rate of A = 1/24 per day, Rate of B = 1/32 per day).
  • Add the individual rates to find their combined rate of work when they work together.
  • Multiply the combined rate by the number of days they worked (8 days) to find the fraction of work completed.
  • Finally, subtract the fraction of work completed from 1 (representing the total work) to find the fraction of work that is left.
  • Carefully read the question to ensure you are answering what is asked (work left vs. work done).
Concept Tested & Keywords
  • Concept Tested: Work and Time problems involving combined work and remaining work.
  • Stem keywords: work, 24 days, 32 days, work together, 8 days, fraction of work is left
  • Lead-in keywords: what fraction

Question ID

Qoe55ItSzOZxoT9Xr1omLD

Practise the full DSSSB - 29 August 2019 (Shift-2)

Attempt every question from this paper in a timed mock, then review the full solution for each one.

More Mathematics Questions

More DSSSB - 29 August 2019 (Shift-2) Questions