DSSSB 13 August 2024
Non Nursing Subjects
Hard

A and B can do a job in 9 days and 20 days, respectively. A works alone for 5 days and leaves. The number of days required by B to complete the remaining job is:

Appeared in: DSSSB 13 August 2024

Explanation

  • First, calculate the fraction of work A completes in 5 days: A's rate is 1/9 per day, so in 5 days, A completes 5 * (1/9) = 5/9 of the job.
  • Next, find the remaining work: Total work is 1, so the remaining portion is 1 - 5/9 = 4/9.
  • Finally, calculate the time B needs to finish this remaining work. B's rate is 1/20 per day.
  • Time = Work / Rate = (4/9) / (1/20) = (4/9) * 20 = 80/9 days.
  • Converting the improper fraction 80/9 to a mixed number gives 8 8/9 days.

Why Other Options Were Wrong

  • Option B: This option, 8 9/9, simplifies to 9. This would mean B takes exactly 9 days. The correct calculation results in 80/9, not 81/9.
  • Option C: This option, 8 0/9, simplifies to 8. This would mean B completes the remaining work in exactly 8 days. In 8 days, B would complete 8 * (1/20) = 8/20 = 2/5 of the job. However, the remaining work is 4/9, which is not equal to 2/5.
  • Option D: This option, 8 5/9, is equal to 77/9. This does not match the calculated time of 80/9 days required for B to finish the remaining 4/9 of the work.

Related Visual

Visual explanation — Related Visual
Clinical Relevance
  • Nursing practice connection: This is primarily an exam-oriented knowledge point with limited direct bedside application, so retain Time and Work as background academic context rather than a clinical decision trigger.
  • While this is a mathematics question, the underlying principle of calculating rates and workload is crucial in healthcare management.
  • It applies to staff scheduling, ensuring adequate nurse-to-patient ratios over a shift.
  • It is also relevant for resource management, such as calculating the consumption rate of medical supplies to predict when to reorder.
How to Approach the Question
  • Identify the time each person takes to complete the job individually. From this, calculate their daily work rate (which is the reciprocal of the time taken).
  • Calculate the amount of work done by the first person (A) during the time they worked alone.
  • Subtract the work done by A from the total work (assumed as 1 unit) to find the remaining work.
  • Divide the remaining work by the daily work rate of the second person (B) to find the number of days B will take to finish.
  • Convert the final fraction into a mixed number if necessary to match the options.
Concept Tested & Keywords
  • Concept Tested: Time and Work
  • Stem keywords: A and B, job, 9 days, 20 days, works alone for 5 days
  • Lead-in keywords: number of days required
  • Negative lead-in flag: false

Question ID

QbVLLPxWzsmpg5vFAuqgdD

Practise the full DSSSB 13 August 2024

Attempt every question from this paper in a timed mock, then review the full solution for each one.

More Mathematics Questions

More DSSSB 13 August 2024 Questions