RML MAINS 2025
Non Nursing Subjects
Medium

If 4 persons can complete a work in 9 days, then in how many days will 6 persons complete the same work?

Appeared in: RML MAINS 2025

Explanation

  • The core principle is that the number of people and the time to complete a fixed amount of work are in inverse proportion.
  • This means if you increase the number of workers, the time taken to complete the work decreases.
  • The total work is constant, calculated as (Number of Persons) × (Number of Days).
  • Given: 4 persons take 9 days. Total work = 4 × 9 = 36 person-days.
  • To find the days (D) for 6 persons: 6 × D = 36, which gives D = 36 / 6 = 6 days.

Why Other Options Were Wrong

  • Option A: If 6 people worked for 5 days, the total work done would be 6 × 5 = 30 person-days, which is less than the required 36 person-days.
  • Option C: If 6 people worked for 7 days, the total work done would be 6 × 7 = 42 person-days, which is more than the required 36 person-days.
  • Option D: This is the time taken by 4 people. Since the number of people has increased to 6, the time taken must decrease.

Related Visual

Visual explanation — Related Visual
Clinical Relevance
  • Nursing practice connection: This is primarily an exam-oriented knowledge point with limited direct bedside application, so retain Inverse Proportion in Time and Work Problems as background academic context rather than a clinical decision trigger.
  • This type of question tests logical reasoning and basic mathematical skills, which are part of the general aptitude section in many nursing entrance exams.
  • Understanding inverse relationships is a fundamental analytical skill applicable in various contexts, not just mathematical problems.
  • For example, in healthcare, the number of available nurses and the time each nurse can spend per patient are often inversely related during a shift.
How to Approach the Question
  • Step 1: Identify the relationship between the variables. Here, the number of persons and the number of days are inversely proportional; as one goes up, the other goes down.
  • Step 2: Calculate the total amount of work required. Total Work = (Initial number of persons) × (Initial number of days).
  • Step 3: Set up the equation for the new scenario using the constant total work: (New number of persons) × (New number of days) = Total Work.
  • Step 4: Solve the equation for the unknown variable, which is the 'New number of days'.
  • Step 5: Perform a logic check. Since more people are working (4 -> 6), the time taken should be less than the original time (9 days). The answer, 6 days, is indeed less than 9.
Concept Tested & Keywords
  • Concept Tested: Inverse Proportion in Time and Work Problems
  • Stem keywords: persons, complete a work, days
  • Lead-in keywords: how many days

Question ID

QOZoYsU1XbCo2lZ3i0-wnv

Practise the full RML MAINS 2025

Attempt every question from this paper in a timed mock, then review the full solution for each one.

More Mathematics [Edition 5] Questions

More RML MAINS 2025 Questions

If 4 persons can complete a work in 9 days, then in how many days will 6 persons complete the same work? - RML MAINS 2025 | NPrep