RML PRE 2025
Non Nursing Subjects
Medium

If 8 workers complete a work in 15 days, then how many days will 10 workers take to complete the same work?

Appeared in: RML PRE 2025

Explanation

  • The problem demonstrates an inverse relationship between the number of workers and the time required to complete a task, assuming the total work remains constant.
  • The total work done is calculated as the product of the number of workers and the number of days, which is 8 workers × 15 days = 120 worker-days.
  • To find the new number of days for 10 workers, the total work (120 worker-days) is divided by the new number of workers (10), resulting in 12 days.
  • Alternatively, using the formula M₁D₁ = M₂D₂, we get 8 × 15 = 10 × D₂, which solves to D₂ = 12.

Why Other Options Were Wrong

  • Option A: This is incorrect. It might be a result of a miscalculation or guessing. Increasing the workforce from 8 to 10 should decrease the time from 15 days, but not necessarily to 10 days.
  • Option C: This is incorrect. The time would remain 15 days only if the number of workers did not change. Since more workers are employed, the time taken must decrease.
  • Option D: This is incorrect. This implies that more workers take more time, which is a direct proportion. Work problems of this nature are based on inverse proportion.

Related Visual

Visual explanation — Related Visual
Clinical Relevance
  • Nursing practice connection: This is primarily an exam-oriented knowledge point with limited direct bedside application, so retain Time and Work Problems as background academic context rather than a clinical decision trigger.
  • This question tests basic numeracy and logical reasoning, skills that are essential for various calculations in clinical practice, such as medication dosage, fluid balance, and staff scheduling.
  • While not a direct clinical scenario, the ability to perform such calculations quickly and accurately is a foundational skill for a nursing professional.
  • What if the question asked how many workers are needed to complete the work in 5 days? Using the same principle (120 worker-days / 5 days), you would find that 24 workers are needed.
How to Approach the Question
  • First, identify the given variables: initial workers (M₁ = 8), initial days (D₁ = 15), and new workers (M₂ = 10).
  • Recognize that the total amount of 'work' is constant. This means the relationship between the number of workers and the days they take is one of inverse proportion.
  • Recall or formulate the equation for inverse proportion: M₁ × D₁ = M₂ × D₂.
  • Substitute the known values into the equation: 8 × 15 = 10 × D₂.
  • Solve for the unknown variable, D₂: Calculate 120 = 10 × D₂, then divide 120 by 10 to get D₂ = 12.
  • Select the option that matches your calculated result.
Concept Tested & Keywords
  • Concept Tested: Time and Work Problems
  • Stem keywords: workers, complete a work, days
  • Lead-in keywords: how many days

Question ID

QMRp03S_jwoKH2-aPbSoqE

Practise the full RML PRE 2025

Attempt every question from this paper in a timed mock, then review the full solution for each one.

More Mathematics Questions

More RML PRE 2025 Questions

If 8 workers complete a work in 15 days, then how many days will 10 workers take to complete the same work? - RML PRE 2025 | NPrep