OSSSC Nursing Officer-2023
Non Nursing Subjects
Hard

'A' can do 1/4 of a work in 6 days and 'B' can do 2/3 of the work in 12 days. In how many days both 'A' and 'B' together can do the work?

Appeared in: OSSSC Nursing Officer-2023

Explanation

  • The core task is to find the combined work rate of A and B to determine how long they take to finish a job together.
  • First, calculate the total time each person takes to complete the work alone. A takes 6 / (1/4) = 24 days. B takes 12 / (2/3) = 18 days.
  • Next, determine their individual daily work rates. A's rate is 1/24 of the work per day, and B's rate is 1/18 of the work per day.
  • Sum the individual rates to find the combined rate: 1/24 + 1/18. The LCM of 24 and 18 is 72. So, (3/72) + (4/72) = 7/72 of the work per day.
  • The time taken to complete the work together is the reciprocal of the combined rate: 1 / (7/72) = 72/7 days.
  • Converting 72/7 to a mixed fraction gives 10 with a remainder of 2, which is 10 2/7 days.

Why Other Options Were Wrong

  • Option A: 4 days is incorrect. This value might be obtained by incorrectly manipulating the given numbers without following the proper work-rate calculation method.
  • Option B: 7 1/2 days (or 7.5 days) is incorrect. This could result from miscalculation, such as incorrectly finding the LCM or adding the fractions.
  • Option D: 12 days is the time it takes for B to complete only 2/3 of the work, not the time for both A and B to complete the entire work together.

Related Visual

Visual explanation — Related Visual
Clinical Relevance
  • Nursing practice connection: This is primarily an exam-oriented knowledge point with limited direct bedside application, so retain Work and Time as background academic context rather than a clinical decision trigger.
  • This is a quantitative aptitude question designed to test logical and mathematical reasoning skills.
  • While not directly related to clinical practice, strong problem-solving skills are essential for nurses in managing time, resources, and patient care tasks efficiently.
  • What if? If A and B worked at the same rate, and each could do 1/2 the work in 9 days, how long would they take together? In that case, each takes 18 days alone. Their combined rate would be 1/18 + 1/18 = 2/18 = 1/9. They would take 9 days together.
How to Approach the Question
  • First, identify the fraction of work done and the time taken by each individual ('A' and 'B').
  • Use this information to calculate the total time each person would take to complete the entire work (1 whole unit) alone. For 'A': if 1/4 work takes 6 days, the whole work takes 6 * 4 = 24 days. For 'B': if 2/3 work takes 12 days, the whole work takes 12 * (3/2) = 18 days.
  • Convert these total times into individual work rates (work per day). The rate is the reciprocal of the time. A's rate = 1/24. B's rate = 1/18.
  • Add the individual rates to find their combined work rate: 1/24 + 1/18.
  • Find the least common multiple (LCM) of the denominators (24 and 18) to add the fractions. The LCM is 72. The combined rate is (3+4)/72 = 7/72.
  • The total time to complete the work together is the reciprocal of the combined rate. Time = 1 / (7/72) = 72/7 days.
Concept Tested & Keywords
  • Concept Tested: Work and Time
  • Stem keywords: work, days, A can do 1/4, B can do 2/3
  • Lead-in keywords: In how many days

Question ID

QelekYqmF1Cgv9EGpMg20w

Practise the full OSSSC Nursing Officer-2023

Attempt every question from this paper in a timed mock, then review the full solution for each one.

More Mathematics Questions

More OSSSC Nursing Officer-2023 Questions

'A' can do 1/4 of a work in 6 days and 'B' can do 2/3 of the work in 12 days. In how many days both 'A' and '… - OSSSC Nursing Officer-2023 | NPrep